The EAC has recommended Terms of Reference for THDC's Pumped Storage project at Humbarli Birmani after an ESZ No Objection Certificate cleared an important regulatory hurdle. The Rs 8,470.89 crore, 1,500 MW project will use 334.82 hectares of land and is planned near environmentally sensitive areas, making Forest and Environmental Clearance critical next steps. The project is expected to generate 3,207.44 MU annually with a projected tariff of Rs 8.07 per kWh. The recommendation marks progress for a major Pumped Storage project while further statutory approvals remain pending. Read verified analysis on EnergylineIndia.com.