• Reviewed IFC drawings, shop drawings, specifications, approved materials and installation details to understand scope, quantities and cost-estimating requirements for mechanical works.
• Prepared and verified material take-offs and quantity inputs for HVAC, firefighting, plumbing, drainage, potable water, irrigation and external utility systems based on drawings and site conditions.
• Checked quantities against actual installation, red-line drawings and approved revisions to identify quantity changes, scope gaps, additions and omissions.
• Reviewed technical issues, drawing discrepancies and procedure conflicts and coordinated with design teams and subcontractors to clarify scope before execution.
• Verified material submittals, technical datasheets, certifications and project specifications, supporting accurate material selection and procurement quantities.
• Coordinated with subcontractors and vendors regarding mechanical materials, fittings, equipment and accessories required for project execution.
• Reviewed pipe routing, fittings, valves, supports, equipment connections and system layouts for constructability and quantity accuracy.
• Supported quantity verification for potable water, drainage, irrigation and firefighting networks including pipelines, valves, hydrants, sprinkler systems, pumps, test headers and accessories.
• Supported quantity verification for HVAC ductwork, insulation, copper piping, FCUs, AHUs/FAHUs, controls and associated accessories.
• Prepared and reviewed MIRs, WIR/RFI, ITPs, method statements, material submittals and red-line drawings, maintaining traceability between scope, quantities and installed works.
• Identified changed works and coordinated corrective actions, helping maintain accurate project records and avoid scope/quantity discrepancies.
• Conducted hydrostatic and system testing for potable, firefighting and irrigation networks, providing field verification of installed systems and quantities.
• Reviewed HVAC duct routing, sealing, insulation and hanging arrangements and supported verification of ductwork and accessories against approved drawings.
• Coordinated consultant inspections and approvals, resolving technical queries that affected quantities, materials and construction scope.