POWERGRID is inviting bids for the establishment of Pune West's 400 kV GIS section and extension of Hinjewadi GIS.
The Substation Package contract carries specification CC/T/W-GIS/DOM/A10/26/14818.
The Substation Package contract has an indicative estimated cost of Rs 111.09 crore and a completion period of 21 months.
The pre-bid meeting is scheduled for 10 November 2026 at 11:30 AM.
Electronic bids must be submitted by 16 November 2026 at 11:00 AM through PRANIT.
Minimum average annual turnover is Rs 81.05 crore, with liquidity or credit access of Rs 13.51 crore.
Class-I local supplier status requires at least 60% local content.
Bid security is replaced by a bid securing declaration, while performance security is generally 10% of the contract price.
EnergylineIndia.com covers this Substation Package contract opportunity for professionals tracking Power Grid projects.