Transmission contractors, equipment suppliers and infrastructure professionals can review a major proposal concerning India's Inter State Transmission System.
The National Committee on Transmission recommended a proposed 1150 kV Western–Eastern Region corridor on 9 November 2026.
The Inter State Transmission System recommendation comprises three packages with a combined estimated cost of ₹68,816 crore.
Project: Western–Eastern Region 1150 kV transmission corridor.
Package 1 estimated cost: ₹18,000 crore.
Package 2 estimated cost: ₹17,000 crore.
Package 3 estimated cost: ₹33,816 crore.
Implementation period: 72 months per package from allocation.
Award approach: Simultaneous awards envisaged.
Planning concern: Demand projections and potential low non-solar utilisation.
Alternative options suggested: 765 kV transmission or extension of a proposed Bhadla-IV direct-current connection.
Committee decision: Recommendation recorded.
Contract awards: Not established by the supplied minutes.
EnergylineIndia.com tracks this Inter State Transmission System development through Transmission infrastructure reports and grid investment updates.