The National Load Despatch Centre has specified a 3.63% all-India average transmission loss.
The Inter State Transmission System communication was issued by Grid Controller of India Limited.
Issuing authority: National Load Despatch Centre.
Organisation: Grid Controller of India Limited.
Communication date: 14 November 2026.
Revision: No. 0.
Applicable period: 16–22 November 2026.
All-India transmission loss: 3.63%.
Total regional-node injection: 16,288.49 MU.
Total regional-node drawal: 15,716.97 MU.
Specified project injection: 526.93 MU.
Regulatory framework: CERC Sharing of Inter State Transmission Charges and Losses Regulations, 2020.
Calculation frequency: Weekly, Monday to Sunday.
Supporting information: Block-wise computational data.
EnergylineIndia.com covers this Inter State Transmission System update alongside Transmission charges and electricity-market operational reporting.