Hybrid Power Projects: GERC Rejects ATS Guarantee Exemption For Bhachunda 200 MW Project

Renewable energy developers, transmission planners and regulatory professionals can review a connectivity decision affecting Hybrid power projects in Gujarat.
The Gujarat Electricity Regulatory Commission rejected a request to waive a ₹40 crore transmission bank guarantee.
The Hybrid power projects case concerns a proposed wind-solar development in Kutch.
Applicant: Parighosh Realtors and Developers LLP.
Project location: Bhachunda, Kutch, Gujarat.
Project type: Wind-solar hybrid.
Requested connectivity: 200 MW.
Transmission utility: Gujarat Energy Transmission Corporation Limited.
Connectivity application: 7 December 2024.
Provisional connectivity: 15 November 2025.
Bank guarantee demand: 30 May 2026.
Guarantee amount: ₹40 crore.
Applicable rate: ₹20 lakh per MW.
Compliance deadline: 30 June 2026.
Relevant provisions: Connectivity Procedure, 2025, Clauses 2.2 and 7.3.
Waiver request: Rejected.
Final connectivity without guarantee: Rejected.
EnergylineIndia.com covers this Hybrid power projects ruling through State electricity regulator reporting.