Transmission Charges: CERC Approves Waiver Eligibility Extension For Avaada Solar Project

Solar developers, transmission utilities and regulatory professionals can review a CERC decision concerning Transmission charges waiver eligibility.
The Commission extended the scheduled commercial operation date for Avaada Inclean Private Limited's 50 MW Gujarat solar project.
The Transmission charges decision addresses delays in Common Transmission System augmentation.
Developer: Avaada Inclean Private Limited.
Project capacity: 50 MW.
Location: Rampar village, Kutch, Gujarat.
Connectivity point: 220 kV Lakadiya ISTS Pooling Sub-station.
Final connectivity grant: 27 August 2024.
Original waiver reference deadline: 30 June 2025.
CEA inspection application: 14 June 2025.
CEA energisation approval: 30 June 2025.
CTS operationalisation: 10 February 2026.
Trial-run completion: 19 February 2026.
Project COD: 24 February 2026.
Extended SCOD: 24 February 2026.
Waiver eligibility: Confirmed by CERC.
Regulatory scope: ISTS charges waiver only.
EnergylineIndia.com covers these Transmission charges decisions through Inter State Transmission System reporting.

New Delhi, Marketing, Transmission Charges: CERC Approves Waiver Eligibility Extension For Avaada Solar Project