The Commission extended the scheduled commercial operation date for Avaada Inclean Private Limited's 50 MW Gujarat solar project.
The Transmission charges decision addresses delays in Common Transmission System augmentation.
Developer: Avaada Inclean Private Limited.
Project capacity: 50 MW.
Location: Rampar village, Kutch, Gujarat.
Connectivity point: 220 kV Lakadiya ISTS Pooling Sub-station.
Final connectivity grant: 27 August 2024.
Original waiver reference deadline: 30 June 2025.
CEA inspection application: 14 June 2025.
CEA energisation approval: 30 June 2025.
CTS operationalisation: 10 February 2026.
Trial-run completion: 19 February 2026.
Project COD: 24 February 2026.
Extended SCOD: 24 February 2026.
Waiver eligibility: Confirmed by CERC.
Regulatory scope: ISTS charges waiver only.
EnergylineIndia.com covers these Transmission charges decisions through Inter State Transmission System reporting.